Bleeding is the upward flow of mixing water in plastic concrete as a result of the settlement of the solids. Delamination occurs when the fresh concrete surface is sealed or densified by troweling while the underlying concrete is still plastic and continues to bleed and/or to release air. Delaminations form fairly late in the finishing process after floating and after the first troweling pass. They can, however, form during the floating operation if the surface is overworked and densified. The chances for delaminations are greatly increased when conditions promote rapid drying of the surface (wind, sun, or low humidity). Drying and higher temperature at the slab surface makes it appear ready to trowel while the underlying concrete is plastic and can still bleed or release air. Vapor retarders placed directly under slabs force bleed water to rise and compound the problem.
Factors that delay initial set of the concrete and reduce the rate of bleeding will increase the chances for delaminations. Entrained air in concrete reduces the rate of bleeding and promotes early finishing that will produce a dense impermeable surface layer. A cool subgrade delays set in the bottom relative to the top layer.
Delamination is more likely to form if:
Corrosion-related delaminations are formed when the upper layer of reinforcing steel rusts thereby breaking the bond between the steel and the surrounding concrete. Corrosion of steel occurs with reduced concrete cover and when the concrete is relatively more permeable causing chlorides to penetrate to the layer of the steel (See CIP 25).
Accelerators or heated concrete often prevent delamination in cool weather.
Be wary of a concrete surface that appears to be ready to trowel before it would normally be expected. Emphasis in finishing should be on screeding, straight-edging, and floating the concrete as rapidly as possible— without working up an excessive layer of mortar and without sealing the surface layer. In initial floating, the float blades should be flat to avoid densifying the surface too early.
Final finishing operations to produce a smooth surface should be delayed as long as possible, and the surface covered with polyethylene or otherwise protected from evaporation.
Delamination may be difficult to detect during finishing operations. If delamination is observed, tear the surface with a wood float and delay finishing as long as possible. Any steps that can be taken to slow evaporation should help.
If a vapor retarder is required, place at least four inches (100 mm) of a trimable, compactible granular fill (not sand). Do not place concrete directly on a vapor retarder. If a moisture-sensitive floor covering will be placed on interior slabs, concrete will generally be placed directly on a vapor retarder (see CIP 29), and other procedures may be necessary.
Do not use air-entrained concrete for interior floor slabs that have a hard troweled surface and that will not be subject to freeze-thaw cycles or deicing salt application. If entrained air is necessary to protect interior slabs from freezing and thawing cycles during construction avoid using air contents over 3%.
Delaminated surfaces can be repaired by patching after the surface layer is removed and the underlying concrete is properly cleaned. Extensive delamination may need to be repaired by grinding and overlaying a new surface. Delaminated surfaces due to steel corrosion will additionally require sandblasting to remove rust from the steel.