Most yield complaints concern a perceived or real deficiency of concrete volume. Concerns about yield should be evaluated using unit weight measurements to calculate the yield. Apparent under-yield occurs when insufficient concrete is ordered to fill the forms and to account for contingencies discussed below. If unit weight and yield calculations indicate an actual under-yield, it should be corrected.
Apparent concrete shortages are sometimes caused for the following reasons:
An over-yield can be an indication of a problem if the excess concrete is caused by too much air or aggregate, or if the forms have not been properly filled.
Differences in batched weights of ingredients and air content in concrete, within the permitted tolerances, can result in discrepancies in yield.
To prevent or minimize concrete yield problems: